Trades follow a sequence dictated by structure, weather and what has to be hidden inside what. Here is the full order, the four rules underneath it, and the decisions that must be locked before each stage.
Trades follow a sequence on a renovation because each stage depends on the one before it, and because most work has to be installed before something else covers it. The general order is: demolition, structural work, roofing and external weatherproofing, rough-in of services, insulation, wall and ceiling linings, waterproofing, tiling, second-fix carpentry, painting, fit-off, then floor coverings.
That order isn't a convention or a preference. It's the physical logic of the building — what has to be structurally supported before anything else happens, what has to be dry before linings go on, and what has to be inside a wall before that wall is closed.
Understanding it is the difference between a renovation that moves and one that stalls.
Reduced to principles, the sequence follows four rules.
Structure before everything. Nothing is worth installing beneath something that still has to be lifted, propped or replaced.
Weathertight before internal. Plaster, insulation and timber all behave badly when wet. Closing the envelope first protects every trade that follows.
Hidden before covering. Anything destined to sit inside a wall, floor or ceiling goes in while that cavity is open. Getting this wrong means opening finished work.
Vulnerable finishes last. The more easily something is damaged, the later it arrives.
Where you're unsure about a particular item, ask which of those four rules applies. It almost always resolves the question.
Most delays on a renovation are not caused by trades. They're caused by a decision that arrives after the trade needed it. These are the ones that bite.
The practical rule: make every selection before demolition starts. Not most of them — all of them. A decision made two weeks late does not cost two weeks. It costs the time until that trade is next free, which is rarely the same thing.
Bathroom. The full sequence in miniature, with waterproofing as the critical path. Nothing can proceed over the membrane until it has cured properly, and the shower screen is measured only after tiling, so it lands at the very end regardless of everything else.
Kitchen. Rough-in matters more than most people expect, because appliance and sink positions drive plumbing and electrical. Cabinetry is templated after linings are complete and walls are square, and benchtops are templated after cabinetry is installed — two sequential measure-and-make steps that cannot be compressed.
Whole-house renovation. Sequencing runs room by room but services run house-wide, so electrical and plumbing rough-in are usually done in one pass across the whole house rather than room by room. Plan around that.
Extension. Runs as a new build until lock-up, then joins the existing house. The junction between old and new — flooring, cornices, roof lines, wall thicknesses — is where the sequence gets complicated, and where making good takes longer than people allow.
It happens on most jobs, and it's usually recoverable if caught early.
The common causes are a late selection, an approval that hasn't landed, a material that hasn't arrived, or something discovered behind a wall during demolition. The consequence is rarely limited to the trade immediately affected — because trades are booked in advance, a stage that slips releases the following trade to another job, and the gap compounds.
What helps: know which items have long lead times and order them first, keep the trade sequence visible to everyone on the job, and when something does slip, tell the following trades immediately rather than hoping to recover. A trade given notice will usually work with you. A trade who arrives to an unready site will not.
Demolition and site preparation, followed by structural work. Nothing internal should begin until the structure is resolved and the building is weathertight.
It depends on the flooring. Tiling generally precedes cabinetry. Timber, carpet and vinyl generally go in after, so they aren't damaged — though some cabinetry is set on finished floors by design. Confirm the approach with your builder before either trade is booked.
Painting usually comes first, with touch-ups after fit-off. Floor coverings are laid late to protect them.
Before rough-in. Once services are in the walls, layout changes mean opening up completed work and re-running plumbing or electrical, which is a variation in both cost and time.
Some can, and a good builder will overlap where it's safe — an electrician and a plumber can often rough in together. What cannot overlap is anything that depends on the previous stage being complete and inspected.
Sequence is one half of a renovation running well. The other is knowing what to check at each stage before it's covered up.
Read next: how to check waterproofing before the tiler starts — the single most consequential inspection in the whole sequence. Or start at Renovations & Extensions for the wider picture.